Industrial Emissions Directive (IED 2.0)
The revised Industrial Emissions Directive is Directive (EU) 2024/1785. Member States had to transpose it by 1 July 2026, and none had notified full transposition by 25 September 2026. Operators need an environmental management system by 1 July 2027, and large pig and poultry farms follow from 2030. The Dutch bill is before the Eerste Kamer.
- Type
- Regulation
- Published
- Reading time
- 6 min
When do the IED 2.0 obligations apply?
Member States had to transpose Directive (EU) 2024/1785 by 1 July 2026. By 25 September 2026 none had notified full transposition, and the European Commission sent all 27, the Netherlands included, a letter of formal notice. The Directive amends the Industrial Emissions Directive, 2010/75/EU, and adds a separate regime for large pig and poultry farms. Operators meet it through national law, in stages: an environmental management system by 1 July 2027, a transformation plan by 30 June 2030 for energy-intensive activities, and the new permit conditions by 1 September 2036 at the latest.
In the Netherlands the implementing bill, Kamerstuk 36864, passed the Tweede Kamer on 16 June 2026. As at 13 October 2026 it is before the Eerste Kamer and has no date of entry into force. The memorie van toelichting puts the number of Dutch installations at about 5,000, from power plants and chemical plants to large pig and poultry farms.
Last updated: 13 October 2026. Checked against the Official Journal text of Directive (EU) 2024/1785, the Commission proposal COM(2025) 986, the Eerste Kamer dossier and explanatory memorandum for bill 36864, and the Commission's infringement decisions of 25 September 2026.
At a glance
Official title
Directive (EU) 2024/1785 of the European Parliament and of the Council of 24 April 2024 amending Directive 2010/75/EU of the European Parliament and of the Council on industrial emissions (integrated pollution prevention and control) and Council Directive 1999/31/EC on the landfill of waste
CELEX
32024L1785 · amends 32010L0075 · corrigendum 32024L1785R(01) for the Hungarian and Italian texts
OJ
OJ L, 2024/1785, 15.7.2024
In force
4 August 2024, the twentieth day after publication (Article 5)
Transposition
By 1 July 2026 (Article 4(1)) · no Member State had notified full transposition by 25 September 2026
Applies to operators
Through national law, in stages: environmental management system by 1 July 2027, transformation plans by 30 June 2030, new permit conditions by 1 September 2036 at the latest (Article 3(2)), pig and poultry farms from 2030 to 2032 by size (indicative, European Commission)
Scope
Annex I industrial activities, about 37,000 installations in the EU · pig and poultry farms above the Annex Ia thresholds, about 38,500 farms (European Commission figures)
Competent authority (NL)
Gedeputeerde staten or the college van burgemeester en wethouders, depending on the activity · supervision and administrative enforcement by the omgevingsdiensten
Dutch implementing act
Bill 36864 amending the Omgevingswet, the Wet milieubeheer and the Wet belastingen op milieugrondslag: passed the Tweede Kamer 16 June 2026; Eerste Kamer committee report 13 July 2026; entry into force by royal decree, no date as at 13 October 2026
Pending amendment
Commission proposal COM(2025) 986 (Omnibus VIII), before the European Parliament's environment committee as at 13 October 2026
What does IED 2.0 add to Directive 2010/75/EU?
Nine changes carry most of the weight for operators. Article numbers refer to Directive 2010/75/EU as amended, except Article 3, which sits in Directive (EU) 2024/1785 itself.
| Change | What it means | Where |
|---|---|---|
Environmental management system | Mandatory for each installation, prepared and implemented by 1 July 2027, with a chemicals inventory and, where required, the transformation plan | Article 14a |
Transformation plans | Indicative plan in the EMS by 30 June 2030 for energy, metals, minerals, chemicals and pulp and paper activities | Article 27d |
Pig and poultry farms | Moved out of the industrial permit chapter into a new chapter with operating rules and thresholds in livestock units (LSU) | Articles 70a to 70i, Annex Ia |
New activities | Battery manufacture from 15,000 tonnes of cells a year, extraction of ores such as lithium, nickel and copper, hydrogen electrolysis above 50 tonnes a day | Annex I, points 2.7, 3.6 and 6.6 |
Emerging techniques | Temporary derogations to test an emerging technique, for up to 30 months in total | Article 27b |
Deep industrial transformation | Compliance period for updated permit conditions extendable to eight years at most | Article 27e |
Penalties | Maximum fine for the most serious infringements by a legal person at least 3% of annual Union turnover | Article 79(2) |
Compensation | Individuals whose health is damaged by an infringement can claim compensation | Article 79a |
Electronic permitting | Member States implement electronic permitting procedures by 31 December 2035 | Article 5(4) |
Who is in scope?
Two groups. The first is industrial installations that carry out an activity in Annex I of Directive 2010/75/EU above its capacity threshold: energy, metals, minerals, chemicals, waste management and other activities such as pulp and paper, textiles and food. The 2024 amendment added three activities. Battery manufacture, other than assembly only, is in from 15,000 tonnes of battery cells a year (point 2.7). Extraction and on-site treatment of fifteen ores on an industrial scale, lithium, cobalt, nickel and copper among them, is in with no tonnage threshold (point 3.6). Electrolysis of water for hydrogen is in above 50 tonnes a day (point 6.6). Under the amended point 6.2, textile pre-treatment, dyeing and finishing count from 10 tonnes a day, and a plant whose only waste activity is anaerobic digestion from 100 tonnes a day.
The second group is pig and poultry farms under Annex Ia: pigs from 350 livestock units (LSU), only laying hens from 300 LSU, other poultry from 280 LSU, and any mix of pigs and poultry from 380 LSU. Organic pig rearing is excluded. Annex Ia fixes what an animal counts for: a breeding sow of 50 kg or more is 0.5 LSU, a piglet up to 20 kg 0.027 and a broiler 0.007. The competent authority may count nearby farms of the same or linked operators as one unit (Article 70b).
Cattle are not covered. Under Article 73(3) the Commission must report by 31 December 2026 on whether Union action is needed on livestock emissions, cattle in particular, with a legislative proposal where appropriate. The Commission counts about 37,000 industrial installations and 38,500 pig and poultry farms under the Directive; in the Netherlands the explanatory memorandum counts about 5,000 installations.
What does IED 2.0 require?
Article 14a
Environmental management system
Each installation needs an EMS prepared and implemented in line with the relevant BAT conclusions by 1 July 2027. It holds environmental objectives and performance indicators, a chemicals inventory and, for energy-intensive activities, the transformation plan. Installations in the activities newly covered by Article 3(4) of Directive (EU) 2024/1785 are not held to the 2027 date.
Articles 14 to 16
Updated permit conditions
For installations already permitted, the amended conditions apply when the permit is granted or updated, within four years of new BAT conclusions published after 1 July 2026, or by 1 September 2036, whichever comes first (Article 3(2) of Directive (EU) 2024/1785). Until then the text in force on 3 August 2024 continues to apply.
Article 27d
Transformation plan
By 30 June 2030, operators of energy, metals, minerals, chemicals and pulp and paper installations add to their EMS an indicative plan for how each installation will change over 2030 to 2050, towards a climate-neutral economy by 2050.
Articles 70a to 70i
Operating rules for farms
Farms above the Annex Ia thresholds follow uniform operating rules set by a Commission implementing act, the UCOL, instead of the industrial permit chapter. National rules apply within 4, 5 or 6 years of that act entering into force, depending on farm size (Article 3(5)).
Article 79
Penalties
For the most serious infringements by a legal person, the maximum fine is at least 3% of the operator's annual Union turnover in the financial year before the fine. Member States may use criminal penalties instead, if they are equally effective, proportionate and dissuasive.
Article 79a
Compensation for health damage
Individuals whose health is damaged by an infringement of the national IED rules can claim compensation from the person responsible. A limitation period may not start before the infringement has ceased and the person knows, or can reasonably be expected to know, of the damage.
The dates
2024
Set by law
Directive (EU) 2024/1785 signed in Strasbourg
Set by law
Directive (EU) 2024/1785 published in the Official Journal
Calculated
Directive (EU) 2024/1785 enters into force
Article 5: the twentieth day after publication.
2025
Set by the Tweede Kamer
Dutch implementing bill 36864 submitted to the Tweede Kamer
Set by the European Commission
Commission proposes Omnibus VIII, COM(2025) 986, which amends the IED
2026
Set by the Tweede Kamer
Tweede Kamer adopts bill 36864
Set by law
Commission adopts a delegated act on the content of transformation plans (Article 27d(5))
We found no adopted act as at 13 October 2026. Omnibus VIII would delete Article 27d.
Set by law
Transposition deadline (Article 4(1))
Also the cut-off in Article 3: BAT conclusions published after this date trigger the four-year periods for applying the new permit conditions.
Set by the Eerste Kamer
Eerste Kamer committee publishes its report on bill 36864
Set by law
Commission adopts implementing acts on farm operating rules (Article 70i(2)) and on the method for assessing compliance with emission limit values (Article 15a(2))
Set by the European Commission
Letters of formal notice to all 27 Member States, the Netherlands included, for not notifying full transposition
Member States have two months to reply.
Set by the European Commission
Commission announces the newly adopted uniform conditions for operating rules for pig and poultry farms (UCOL)
We found no Official Journal publication or entry into force date as at 13 October 2026.
Indicative: European Parliament Legislative Observatory, as at 13 October 2026
Parliament plenary, first reading of Omnibus VIII
Set by law
Commission reports on Union action on livestock emissions, cattle in particular (Article 73(3))
2027
Set by law
Operators prepare and implement the environmental management system (Article 14a(4))
Installations under Article 3(4) of Directive (EU) 2024/1785 excepted.
2028
Set by law
Commission report on implementation, then every five years (Article 73(1))
Set by law
Commission guidelines on counting nearby livestock installations as one (Article 70b(2))
2030
Indicative: European Commission, 8 October 2026
UCOL starts applying to pig and poultry farms, by size
Article 3(5): 4 years after the UCOL enters into force for farms of 600 LSU or more, 5 years for 400 LSU or more, 6 years for the rest.
Set by law
Transformation plans included in the EMS (Article 27d(1))
Calculated
Latest reassessment of BAT-AEL derogations granted before 1 July 2026 (Article 3(6)), and newly covered cold-rolling and textile installations in operation before 1 July 2026 comply (Article 3(3))
Both run four years from 1 July 2026.
Proposed (COM(2025) 986)
Environmental management system deadline moved from 1 July 2027
Only if Omnibus VIII is adopted in this form.
2034
Set by law
Latest date for newly covered gasification, smithery, battery and ore-extraction installations (Article 3(4))
2035
Set by law
Member States implement electronic permitting (Article 5(4))
2036
Set by law
Latest date for permitted installations to meet the amended permit conditions (Article 3(2))
Without an official date
No official dateProposed (bill 36864)
The Dutch implementing law enters into force
The bill leaves the date to royal decree. The explanatory memorandum aimed for 1 July 2026.
Who supervises IED 2.0 in the Netherlands?
No single national supervisor does. Under the Omgevingswet the competent authority is the provincial executive (gedeputeerde staten) or the municipal executive (college van burgemeester en wethouders), depending on the activity, and the omgevingsdiensten carry out supervision and administrative enforcement for them. Criminal enforcement runs through the Wet op de economische delicten. The explanatory memorandum takes the position that Dutch law already meets the 3% minimum in Article 79(2), because Article 23(7) of the Wetboek van Strafrecht allows a fine of up to ten percent of a legal person's annual turnover where the highest fine category is not an appropriate punishment.
The bill amends the Omgevingswet, the Wet milieubeheer and the Wet belastingen op milieugrondslag, and also carries out the Industrial Emissions Portal Regulation, (EU) 2024/1244. Transitional law goes into a separate algemene maatregel van bestuur, which the memorandum planned to bring into force with the bill on 1 July 2026. That date has passed. As at 13 October 2026 the bill awaits the government's reply to the Eerste Kamer committee's report of 13 July 2026, and entry into force will be set by royal decree.
What would Omnibus VIII change?
On 10 December 2025 the Commission proposed COM(2025) 986, part of its environmental simplification package. It would amend Directive 2010/75/EU and Directive (EU) 2024/1785 again. As at 13 October 2026 the Legislative Observatory records it as awaiting a committee decision in Parliament, and records no Council position. Once adopted, the proposal gives Member States 24 months from its entry into force to transpose it.
| Provision | Directive as adopted | Proposal COM(2025) 986 |
|---|---|---|
EMS deadline | 1 July 2027 | 1 July 2030 |
Chemicals inventory in the EMS | Required | Removed |
EMS audit | Required | Removed |
Transformation plans (Article 27d) | By 30 June 2030 | Article deleted |
Organic poultry farms | In scope above the Annex Ia thresholds | Out of scope |
Unweaned piglets | Counted towards farm capacity | Not counted |
Transitional provisions | Article 3 of Directive (EU) 2024/1785 | Moved to Article 82 of Directive 2010/75/EU |
What has changed?
8 October 2026. The Commission announced the newly adopted uniform conditions for operating rules for pig and poultry farms. Article 70i(2) set 1 September 2026 as the deadline.
25 September 2026. The Commission sent letters of formal notice to all 27 Member States for not notifying full transposition. They have two months to reply.
13 July 2026. The Eerste Kamer committee published its report on bill 36864.
1 July 2026. The transposition deadline passed without a Dutch implementing law in force.
16 June 2026. The Tweede Kamer adopted bill 36864.
10 December 2025. The Commission proposed Omnibus VIII, COM(2025) 986, which would move the EMS deadline to 1 July 2030 and delete the transformation plan duty.
Check your sites against Annex I and Annex Ia
Book a working session and we will map your installations against the Annex I activities and the Annex Ia livestock thresholds, naming the article and the source for each conclusion.
Questions and answers
When does IED 2.0 apply?
Directive (EU) 2024/1785 entered into force on 4 August 2024 and had to be transposed by 1 July 2026. Operators meet it through national law, in stages: an environmental management system by 1 July 2027, a transformation plan by 30 June 2030 for energy-intensive activities, and the amended permit conditions by 1 September 2036 at the latest. Pig and poultry farms follow from 2030 to 2032, depending on size.
Has the Netherlands transposed IED 2.0?
Not as at 13 October 2026. Bill 36864 passed the Tweede Kamer on 16 June 2026 and is before the Eerste Kamer, with entry into force left to royal decree. The deadline was 1 July 2026. On 25 September 2026 the Commission sent the Netherlands and the other 26 Member States a letter of formal notice for not notifying full transposition.
Which pig and poultry farms does IED 2.0 cover?
Under Annex Ia: pig farms from 350 livestock units, farms with only laying hens from 300, other poultry from 280, and mixed pig and poultry farms from 380. Organic pig rearing is excluded. These farms follow uniform operating rules set by the Commission rather than an industrial permit, from 2030 to 2032 depending on size.
Does IED 2.0 cover cattle farms?
No. Cattle are outside Annex Ia. Article 73(3) of Directive 2010/75/EU, as amended, requires the Commission to report by 31 December 2026 on whether Union action is needed on livestock emissions, cattle in particular, and to add a legislative proposal where appropriate.
How high can IED 2.0 fines be?
For the most serious infringements by a legal person, Article 79(2) requires a maximum fine of at least 3% of the operator's annual Union turnover in the preceding financial year. In the Netherlands enforcement runs through the Wet op de economische delicten, and the government relies on Article 23(7) of the Wetboek van Strafrecht, which allows fines of up to ten percent of annual turnover.
Will the IED 2.0 environmental management system deadline move to 2030?
Only if Omnibus VIII, COM(2025) 986, is adopted in that form. It would move the date from 1 July 2027 to 1 July 2030 and remove the chemicals inventory and the audit. As at 13 October 2026 the proposal is still before the European Parliament's committee, so 1 July 2027 is the date in the adopted Directive.
Who is the competent authority for an IED installation in the Netherlands?
The provincial executive (gedeputeerde staten) or the municipal executive (college van burgemeester en wethouders), depending on the activity. The omgevingsdiensten carry out supervision and administrative enforcement for them, and criminal enforcement runs through the Wet op de economische delicten.
Sources
Directive (EU) 2024/1785 amending Directive 2010/75/EU on industrial emissions and Council Directive 1999/31/EC on the landfill of wasteEUR-Lex · 15 July 2024
Directive 2010/75/EU on industrial emissions (integrated pollution prevention and control)EUR-Lex
Proposal COM(2025) 986 amending Directives 2008/98/EC, 2010/75/EU, (EU) 2015/2193 and (EU) 2024/1785EUR-Lex · 10 December 2025
Procedure file 2025/0394(COD): Omnibus VIII on environmental legislationEuropean Parliament Legislative Observatory
Commission takes action to ensure complete and timely transposition of EU directives (INF/26/1834)European Commission · 25 September 2026
Show all 10 sourcesShow the first 6 only
Industrial and Livestock Rearing Emissions Directive (IED 2.0)European Commission
New EU emissions framework: simpler rules for pig and poultry farmersEuropean Commission · 8 October 2026
Implementatie herziening Richtlijn industriële emissies en de uitvoering van de PIE-verordening (36.864)Eerste Kamer
Kamerstuk 36864, nr. 3: Memorie van toelichtingOfficiële bekendmakingen · 25 November 2025
Related
Glossary · 25
Compliance assurance
Mechanisms for securing compliance using three categories of intervention: compliance promotion; compliance monitoring; follow-up and enforcement.
Emission levels associated with emerging techniques
The range of emission levels obtained under normal operating conditions using an emerging technique or a combination of emerging techniques, as described in BAT conclusions, expressed as an average over a given period of time, under specified reference conditions
A standard measurement unit that allows for the aggregation of the various categories of livestock in order for them to be compared, and is calculated by using the coefficients for individual livestock categories listed in Annex Ia
All actions, including site visits, monitoring of emissions and checks of internal reports and follow-up documents, verification of self-monitoring, checking of the techniques used and adequacy of the environment management of the installation, undertaken by or on behalf of the competent authority to check and promote compliance of installations with their permit conditions and, where necessary, to monitor their environmental impact
Baseline report
Information on the state of soil and groundwater contamination by relevant hazardous substances
The public affected or likely to be affected by, or having an interest in, the taking of a decision on the granting or the updating of a permit or of permit conditions; for the purposes of this definition, non-governmental organisations promoting the protection of human health or the environment and meeting any requirements under national law shall be deemed to have an interest
A novel technique for an industrial activity that, if commercially developed, could provide either a higher general level of protection of human health and the environment or at least the same level of protection of human health and the environment and higher cost savings than existing best available techniques
Benchmarks
The indicative range of environmental performance levels associated with best available techniques, which is to be used as a reference in the EMS
Show all 25Show fewer
Environmental performance levels associated with the best available techniques
The range of environmental performance levels, obtained under normal operating conditions using a BAT or a combination of BATs; as described in BAT conclusions
Emission levels associated with the best available techniques
The range of emission levels obtained under normal operating conditions using a best available technique or a combination of best available techniques, as described in BAT conclusions, expressed as an average over a given period of time, under specified reference conditions
The rules included in permits or general binding rules for the operation of activities referred to in Annex Ia, setting out the emission limit values, the environmental performance limit values, associated monitoring requirements, and, where relevant, land spreading practices, pollution prevention and mitigation practices, nutritional management, feed preparation, housing, manure management, including collection, storage, processing and land spreading of manure, and storage of dead animals, and which are consistent with the use of best available techniques
A document containing the parts of a BAT reference document laying down the conclusions on best available techniques and emerging techniques, their description, information to assess their applicability, the emission levels associated with those techniques, the environmental performance levels associated with those techniques, the content of an environmental management system including benchmarks, associated monitoring, associated consumption levels and, where appropriate, relevant site remediation measures
A document, resulting from the exchange of information organised pursuant to Article 13, drawn up for defined activities and describing, in particular, applied techniques, present emissions and consumption levels, techniques considered for the determination of best available techniques as well as BAT conclusions and any emerging techniques, giving special consideration to the criteria listed in Annex III
Deep industrial transformation
The implementation by industrial operators of emerging techniques or best available techniques involving a major change in the design or technology of all or part of an installation or the replacement of an existing installation by a new installation, which allows an extremely substantial reduction of emissions of greenhouse gases in line with the objective of climate neutrality and optimises environmental co-benefits, at least to the levels that can be achieved by techniques identified in the applicable BAT conclusions, taking into account cross-media effects
A change in the nature or functioning, or an extension, of an installation or combustion plant, waste incineration plant or waste co-incineration plant which may have significant negative effects on human health or the environment
Emission limit values or other conditions, at least at sector level, that are adopted with the intention of being used directly to set permit conditions
A written authorisation to operate all or part of an installation or combustion plant, waste incineration plant or waste co-incineration plant
Environmental quality standard
The set of requirements which must be fulfilled at a given time by a given environment or particular part thereof, as set out in Union law
Environmental performance limit value
A performance value included in a permit, expressed for specified conditions in terms of certain specific parameters
The mass, expressed in terms of certain specific parameters, concentration and/or level of an emission, which may not be exceeded during one or more periods of time
Emission
The direct or indirect release of substances, vibrations, heat or noise from individual or diffuse sources in the installation into air, water or land
The direct or indirect introduction, as a result of human activity, of substances, vibrations, heat, noise or odours into air, water or land, which can be harmful to human health or the quality of the environment, result in damage to material property, or impair or interfere with amenities and other legitimate uses of the environment
Any natural or legal person who operates or controls in whole or in part the installation or combustion plant, waste incineration plant or waste co-incineration plant or, where this is provided for in national law, to whom decisive economic power over the technical functioning of the installation or plant has been delegated
A stationary technical unit within which one or more activities listed in Annex I, in Annex Ia or in Part 1 of Annex VII are carried out, and any other directly associated activities on the same site which have a technical connection with the activities listed in those Annexes and which could have an effect on emissions and pollution
The most effective and advanced stage in the development of activities and their methods of operation which indicates the practical suitability of particular techniques for providing the basis for emission limit values and other permit conditions designed to prevent and, where that is not practicable, to reduce emissions and the impact on the environment as a whole: (a) ‘techniques’ includes both the technology used and the way in which the installation is designed, built, maintained, operated and decommissioned; (b) ‘available techniques’ means techniques developed on a scale which allows implementation in the relevant industrial sector, under economically and technically viable conditions, taking into consideration the costs and advantages, regardless of whether such techniques are used or produced in the Union, as long as they are reasonably accessible to the operator; (c) ‘best’ means most effective in achieving a high general level of protection of the environment as a whole, including human health and climate protection